Storm Water Management Pond

Nellis Construction was awarded the contract for the construction of a large storm water management pond in Milton, Ontario. This pond was designed to service the future industrial sites along the James Snow Parkway. Work began in July 2011. Topsoil was stripped and stockpiled for reuse. The pond was excavated to the design grade, topsoil was placed back on the slopes of the pond to support plant life.

Grading was performed using a GPS guided dozer.